Multiple Choice
A guide who leads the project team through an analysis of project activities that went well and of what needs improvement and aids in the development of a follow-up action plan with goals and accountability is a(n)
A) Owner.
B) Project sponsor.
C) Project manager.
D) Project facilitator.
E) Mediator.
Correct Answer:

Verified
Correct Answer:
Verified