Multiple Choice
The final step in the project control process for measuring and evaluating project performance is to
A) Take appropriate action.
B) Prepare a report to top management.
C) Follow up on corrective action.
D) Measure progress and performance.
E) Review spending with team members.
Correct Answer:

Verified
Correct Answer:
Verified