Multiple Choice
The earned value system starts with the time-phased costs that provide the project baseline, which is called the
A) Planned budgeted value of work scheduled.
B) Planned budgeted value of work completed.
C) Earned value of work scheduled.
D) Scheduled value of work scheduled.
E) Scheduled value of work completed.