Multiple Choice
When interacting with the customer, it is important that the project manager
A) Show the customer your knowledge on the subject by using technical terms.
B) Speak slowly and in precise terms.
C) Speak the language of the customer.
D) Allow only one person from the project team to communicate with the customer.
E) Ask the customer to repeat important details.
Correct Answer:

Verified
Correct Answer:
Verified
Q20: Not only can contracted project work be
Q22: Positive relationships going into a negotiation can
Q24: Co-Locating staff for a project is a
Q28: _ satisfaction is measured by the ratio
Q29: Key practices in the partnering approach to
Q30: When negotiating, the tendency is to want
Q44: Conflict is inevitable on a project; however,
Q72: Experience indicates that co-location of project teams
Q78: In the traditional method of managing projects,
Q97: Security issues on an outsourced project can