Multiple Choice
Adverse weather, design flaws, and equipment breakdown can create negative slack.This is an example of reducing project duration caused by
A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Correct Answer:

Verified
Correct Answer:
Verified