Multiple Choice
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
A) Normal
B) Reserve
C) Crash
D) Accelerated
E) Expedited
Correct Answer:

Verified
Correct Answer:
Verified