Multiple Choice
Which of the following projects would be least benefited if additional resources were added?
A) Splitting and stacking a cord of wood
B) Developing new software
C) Harvesting a crop by hand
D) Building a cabin
E) Moving to a new house
Correct Answer:

Verified
Correct Answer:
Verified