Compressing Activities on a Project with a Sensitive Project Network

Question 42

Multiple Choice

Compressing activities on a project with a sensitive project network will:


A) Increase risk of delaying the project.
B) Improve cost-time crashing success.
C) Reduce scheduling flexibility.
D) Increase risk of delaying the project and reduce scheduling flexibility.

Correct Answer:

verifed

Verified