Multiple Choice
Compressing activities on a project with a sensitive project network will:
A) Increase risk of delaying the project.
B) Improve cost-time crashing success.
C) Reduce scheduling flexibility.
D) Increase risk of delaying the project and reduce scheduling flexibility.
Correct Answer:

Verified
Correct Answer:
Verified