Multiple Choice
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?
A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network.
Correct Answer:

Verified
Correct Answer:
Verified