Sam, the Project Engineer, Has Been Scheduled to Run the Product

Question 75

Multiple Choice

Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of what type of resource constraint?


A) Physical
B) Technical
C) People
D) Equipment
E) Time