Solved

Gene Is Trying to Order the Concrete Needed to Continue

Question 32

Multiple Choice

Gene is trying to order the concrete needed to continue his project.However, the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions