Multiple Choice
Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?
A) Resources have been assigned to each activity so they are adequate to complete the project on time.
B) Technical dependencies between activities are known.
C) The project completion date can be established.
D) The project is ready to be implemented.
E) All of these are true statements once technical constraints have been established.
Correct Answer:

Verified
Correct Answer:
Verified
Q48: Identify and give an example of the
Q49: Identify and briefly describe two ways to
Q50: A(n) _ constraint addresses the sequence in
Q51: If it becomes necessary to delay one
Q52: Resource leveling or smoothing can have all
Q54: A project scheduler is trying to reallocate
Q55: When scheduling activities in a resource-constrained project,
Q56: If your project has spent $75,000 versus
Q57: The fact that you must pour foundation
Q58: When only one person is responsible for