Multiple Choice
Resource leveling or smoothing can have all the following results on a project EXCEPT
A) Lower peak resource demand.
B) Reduced resource need over the life of the project.
C) Reduced fluctuations in resource demand.
D) A longer project duration.
E) A more sensitive network.
Correct Answer:

Verified
Correct Answer:
Verified