Multiple Choice
In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
A) Smallest duration.
B) Least slack.
C) Most slack.
D) Lowest identification number.
E) Highest cost.
Correct Answer:

Verified
Correct Answer:
Verified