Multiple Choice
Splitting an activity can result in all of the following EXCEPT
A) More people working on the same activity.
B) Possible startup and shutdown costs.
C) A resource being moved from one activity to another and then back.
D) Activity work being placed on hold for a period until more resources are available.
E) A better project schedule.
Correct Answer:

Verified
Correct Answer:
Verified