The Amount of Delay Within a Task That Will Not

Question 11

Multiple Choice

The amount of delay within a task that will not delay the overall project is known as a


A) Total Slack.
B) Estimated Effort.
C) Opportunity Cost.
D) Both Total Slack and Opportunity Cost are correct.

Correct Answer: