    The Longest Path Through a Project Network Is Called the _________
Solved

The Longest Path Through a Project Network Is Called the _________

Question 18

Question 18

Short Answer

The longest path through a project network is called the _________.

Correct Answer:

verifed

Verified

critical path
Explanation: The...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q6: If, for some reason, the project must

Q13: A project network provides the basis for

Q16: Activities which can take place at the

Q17: _ activities must be completed immediately before

Q19: After the total slack for each activity

Q54: It is possible for a project network

Q77: System documentation cannot end until three days

Q81: What is a hammock activity and give

Q114: In developing a project network, neither looping

Q125: If testing cannot be completed any earlier

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines