Jose Is Forecasting Project Time and Cost for Constructing a New

Question 66

Multiple Choice

Jose is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount.Which of the following methods is he using?


A) Ratio
B) Template
C) Apportion
D) Function point
E) Learning curve

Correct Answer: