    Large Projects That Have Long Time Horizons and a Very
Solved

Large Projects That Have Long Time Horizons and a Very

Question 60

Question 60

Multiple Choice

Large projects that have long time horizons and a very high complexity can be referred to as


A) Mega Projects.
B) High Risk.
C) White Elephants.
D) Both Mega Projects and White Elephants.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: Estimates are supposed to be based on

Q56: The top-down method of estimating project time

Q57: The estimating factor that considers the skill

Q61: Costs that are associated with time devoted

Q62: Which of the following is NOT one

Q64: A way to improve estimates on future

Q68: What is the relationship between organizational culture

Q71: General and administrative costs are usually allocated

Q81: Under what conditions would the top-down approach

Q90: Cost, time, and budget estimates are the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines