Short Answer
The estimating approach that is best to use on projects where there is an unusual amount of uncertainty surrounding the project and when it is impractical to estimate times and costs for the entire project is known as ___________.
Correct Answer:

Verified
phase estimating
Explanation: Some proje...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Explanation: Some proje...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q18: One guideline to follow when estimating time,
Q27: The salary of the project manager would
Q30: Estimates that are typically based on estimates
Q50: Top-down estimates usually are derived from someone
Q75: The information necessary to conduct a bottom-up
Q76: Rob is responsible for estimating a work
Q77: In practice, estimating processes are frequently classified
Q79: Reasons why estimating time and cost are
Q80: When work package estimates are made by
Q82: Sean is forecasting the time and cost