The Estimating Approach That Is Best to Use on Projects

Question 78

Short Answer

The estimating approach that is best to use on projects where there is an unusual amount of uncertainty surrounding the project and when it is impractical to estimate times and costs for the entire project is known as ___________.

Correct Answer:

verifed

Verified

phase estimating
Explanation: Some proje...