Multiple Choice
"To construct a high-quality, custom home within five months at costs not to exceed $150,000" is best classified as
A) A deliverable.
B) A milestone.
C) An objective.
D) A limit.
E) An exclusion.
Correct Answer:

Verified
Correct Answer:
Verified