Multiple Choice
All of the following are ways the WBS helps in managing projects EXCEPT
A) With cost and time estimates the WBS makes it possible to plan, schedule and budget the project.
B) It provides management with information appropriate to each level.
C) Can be used to define communication channels.
D) Allows the project manager to establish the overall objective of the project.
E) As it is developed, organizational units and individuals can be assigned responsibility of work packages.
Correct Answer:

Verified
Correct Answer:
Verified
Q45: A communication plan should include limits on
Q48: If a project criterion should be optimized
Q62: Having a strong communication plan can go
Q63: The highest element in the hierarchical breakdown
Q64: The ability of a 911 emergency system
Q65: A key aspect to communication plans are
Q66: The final step in defining a project
Q69: After reviewing the project scope statement, the
Q71: In making project trade-offs, a criterion that
Q77: Responsibility Matrices are useful for assigning and