Multiple Choice
Which of the following is least likely to be included in a work package?
A) How long the work package should take to complete
B) A description of work to be performed
C) Overhead expenses
D) How much the work package should cost to complete
E) The person responsible for the work package
Correct Answer:

Verified
Correct Answer:
Verified