Multiple Choice
Which of the following is NOT considered to be a characteristic of a project?
A) An established objective
B) A clear beginning and end
C) Specific time, cost and performance requirements
D) For internal use only
E) Something never been done by a particular company before
Correct Answer:

Verified
Correct Answer:
Verified