The planned order releases in week 5 are 100 units.Each unit must be processed for 5 minutes at the work station.If the available capacity at the work station is one hour:
A) Overtime will be needed.
B) Delivery lead times should be increased.
C) The work station is underloaded.
D) An order backlog will be created