Question 34

Multiple Choice

A company must make 400 units per day.The company works one 12-hour shift.What is the efficiency if the total time to complete all tasks is 23 minutes and the company is using 18 workstations?


A) 22%
B) 71%
C) 50%
D) 88%

Correct Answer: