    An FMEA Estimates the Risk Priority Number (RPN)for a Given
Solved

An FMEA Estimates the Risk Priority Number (RPN)for a Given

Question 21

Question 21

Multiple Choice

An FMEA estimates the risk priority number (RPN) for a given failure mode to be 36.The occurrence rating is 3 and the severity rating is 3.Thus,the undetectability rating is:


A) 3
B) 4
C) 5
D) 6

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: The main purpose of quality function deployment

Q17: Xanadu Inc.has a project team interested in

Q18: Another way to think of how virtual

Q19: Overall,it is clear that well-managed innovation projects:<br>A)Apply

Q20: A disadvantage of "component standardization" is that

Q22: _ transform product specifications and new process

Q23: The stage of the product life cycle

Q24: Suppose that you want to develop a

Q25: Understanding the product life cycle is important

Q26: A FMEA analysis shows that,for a given

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines