Multiple Choice
A project offers a 30% probability of a payoff after one year of $2 million and a 70% chance of a payoff of $1 million.What is the maximum you would invest in this project today if the discount rate is 10%?
A) $818,181.82
B) $1,181,818.18
C) $1,300,000.00
D) $1,430,000.00
Correct Answer:

Verified
Correct Answer:
Verified