A project is expected to increase inventory by $17,000,increase accounts payable by $10,000,and decrease accounts receivable by $1,000.What is the project's cash flow from net working capital at time zero?
A) −$8,000
B) $8,000
C) −$6,000
D) $6,000
Correct Answer:

Verified
Correct Answer:
Verified