Multiple Choice
Net working capital is expected to increase by $25,000 in year 5 of a project.If this extra working capital is recovered when the project ends in year 6,what is the effect on the project's net present value,if the cost of capital is 15%?
A) NPV will not be affected because the $25,000 will all be recouped.
B) NPV will increase by $12,429.42.
C) NPV will decrease by $25,000.
D) NPV will decrease by $1,621.23.
Correct Answer:

Verified
Correct Answer:
Verified
Q49: In the MACRS depreciation schedules,the depreciation percentage
Q50: Capital budgeting analysis focuses on cash flow
Q51: An asset in the MACRS 5-year class
Q52: A new project requires an increase in
Q53: Which one of the following would not
Q55: Opportunity costs are evaluated for investment decisions
Q56: In project analysis,allocations of overhead should be
Q57: What is the effect of using MACRS
Q58: What nominal annual return is required on
Q59: A firm invests in a 7-year project