Which of the following most closely describes net material requirements in an MRP system?


A) Gross requirements - planned receipts.
B) Gross requirements - (on-hand + scheduled receipts) .
C) Gross requirements - on-hand + scheduled receipts.
D) Gross requirements - planned order releases.

Correct Answer: