Which of the Following Is Correct Regarding Future Demand for Component

Question 42

Multiple Choice

Which of the following is correct regarding future demand for component parts?


A) Future demand in an order-point system is based on the master production schedule.
B) Future demand in an MRP system is based on the past history of demand for each component part.
C) Future demand in an MRP system is based on the master production schedule.
D) None of the above.

Correct Answer: