Multiple Choice
The longest series of connections in the project network from the start to the end of the activities is also referred to as
A) the action path.
B) the critical path.
C) the master schedule.
D) float or slack.
Correct Answer:

Verified
Correct Answer:
Verified
Q29: The information calculated from the forward and
Q30: Project management requires<br>A) scheduling, planning, and controlling.<br>B)
Q31: "Slack" refers to the difference between<br>A) late
Q32: Which of the following statements concerning project
Q33: A forward pass of the above network
Q34: Which of the following is NOT included
Q35: The advantage(s)of the network method over the
Q36: Project control is best maintained by<br>A) the
Q38: Given the information above,what is the LS
Q39: Multiple critical paths can exist under the