Which of the following statements is NOT correct about Gantt charts?
A) Gantt charts are extremely easy to use and are quite well understood.
B) Gantt charts show not only the time required for an activity but also the time at which a particular activity takes place.
C) Gantt charts show the interdependencies and relationships between activities.
D) Gantt charts can also be used while scheduling service operations.