Multiple Choice
In project management,a work breakdown structure is
A) a listing of the work assignments given to the project team members.
B) a detailed time schedule for each project activity.
C) a top-down listing of all the tasks needed to complete a project.
D) none of the above.
Correct Answer:

Verified
Correct Answer:
Verified