Which of the Following Statements Is NOT Correct

Question 13

Multiple Choice

Which of the following statements is NOT correct?


A) Six sigma projects require measurement of financial impact be closely tracked, compared to lean projects that do not insist on financial tracking.
B) Six sigma relies more on dedicated experts to guide projects as compared to lean.
C) Lean projects tend to be smaller and simpler compared to six sigma projects.
D) Lean projects tend to support strategic priorities more than is the case for six sigma projects.