Hillier Construction Ltd Commenced the Construction of a Building on 1
Question 2
Question 2
Multiple Choice
Hillier Construction Ltd commenced the construction of a building on 1 July 2013.It has a fixed-price contract for total revenues of $45 million.The expected completion date is 30 June 2016.The expected total cost to Hillier Construction at the beginning of the project is $35 million.The following information relates only to the construction of this building: For the year ending 30 June Costs for the year Costs incurred to date Estimated costs to complete Progress billings during the year Cash collected during the year 2014($000) 12500125002300010000100002015($000) 1500027500850012000110002016($000) 1000037500−2300024000 Hillier Construction uses the percentage-of-completion method based on cost to account for its construction contracts.What are the journal entries for the year ended 30 June 2014 (rounded to the nearest $000) ?
A) DrCrDrCrDrCrDrCr Construction expenses Materials, cash, etc. Accounts receivable Revenue from long-term contract Cash Accounts receivable Construction in progress Gross profit on construction contract $0001250010000100003345$0001250010000100003345 B) DrCrDrCrDrCrDrDrCr Construction in progress Materials, cash, etc. Accounts receivable Revenue from long-term contract Cash Accounts receivable Construction in progress Construction expenses Revenue from long-term contract $000125001000010000357112500$00012500100001000016071 C) DrCrDrCrDrCrDrDrCr Construction in progress Materials, cash, etc. Accounts receivable Billings on construction in progress Cash Accounts receivable Construction in progress Construction expenses Revenue from long-term contract $000125001000010000334512500$00012500100001000015845 D) DrCrDrCrDrCrDrCr Construction in progress Materials, cash, etc. Accounts receivable Billings on construction in progress Cash Accounts receivable Construction expenses Revenue from long-term contract $00012500100001000012500$00012500100001000012500