Multiple Choice
Cantor's has been busy analyzing a new product.Thus far,management has determined that an OCF of $218,200 will result in a zero net present value for the project,which is the minimum requirement for project acceptance.The fixed costs are $329,000 and the contribution margin per unit is $211.The company feels that it can realistically capture 2.5 percent of the 110,000 unit market for this product.The tax rate is 34 percent and the required rate of return is 11 percent.Should the company develop the new product? Why or why not?
A) Yes; The project's required rate of return exceeds the expected IRR.
B) Yes; The expected level of sales exceeds the required level of production.
C) No; The required level of production exceeds the expected level of sales.
D) No; The IRR is less than the required rate of return.
E) No; The project will never payback on a discounted basis.
Correct Answer:

Verified
Correct Answer:
Verified
Q40: Webster Iron Works started a new project
Q57: Uptown Promotions has three divisions.As part of
Q59: You are in charge of a project
Q60: Steve is fairly cautious when analyzing a
Q61: By definition,which one of the following must
Q63: Which one of the following statements concerning
Q64: A proposed project has fixed costs of
Q65: Precise Machinery is analyzing a proposed project.The
Q66: The accounting break-even production quantity for a
Q67: Precise Machinery is analyzing a proposed project.The