Multiple Choice
When the present value of the cash inflows exceeds the initial cost of a project,then the project should be:
A) accepted because the internal rate of return is positive.
B) accepted because the profitability index is greater than 1.
C) accepted because the profitability index is negative.
D) rejected because the internal rate of return is negative.
E) rejected because the net present value is negative.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: Graphing the crossover point helps explain: <br>A) why
Q56: You are analyzing the following two mutually
Q57: The length of time a firm must
Q58: In actual practice,managers frequently use the:<br>I.average accounting
Q59: The relevant discount rate for the following
Q61: An investment project provides cash flows of
Q63: It will cost $6,000 to acquire an
Q64: Roger's Meat Market is considering two independent
Q65: Why is payback often used as the
Q71: A project has a net present value