Consider a three sequentially stepped process named as Process A, Process B and Process C.Input comes into Process A.Output form A goes into Process B.Output from B goes into Process C.Output of C is the final output.Suppose that it takes 2 minutes per unit in Process A, 3 minutes per unit in Process B and 1 minute per unit in Process C.What will be maximum steady state output from this system?
A) 30 per hour
B) 60 per hour
C) 20 per hour
D) 10 per hour
E) cannot tell since it depends on the input rate.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Which of the following best describes the
Q3: Benchmarking refers to the practice of comparing
Q4: Efficiency of a production process is the
Q13: Make-to-order production processes are well suited for
Q17: A bottleneck occurs when a stage in
Q22: If you want to reduce process flow
Q24: Throughput rate of a production process is
Q36: To reduce process flow time, you might
Q39: Process analysis can help answer many important
Q47: A process flowchart uses which of the