A Simple Project Listing of Five Activities, Their Predecessors, and Their

Question 36

Multiple Choice

A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:
Using the CPM, which activities have slack in this project?


A) A
B) B
C) C
D) D
E) C and E