Multiple Choice
A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?
A) It specifies the relationships in the CPM network of activities.
B) It provides useful timing information.
C) It includes cost information.
D) It is the probability information required in the final step of CPM.
E) None of these
Correct Answer:

Verified
Correct Answer:
Verified