You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here.
The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.If you crash this project by one day,
What is the total (i.e., direct and indirect) project cost?
A) $2,150
B) $2,300
C) $2,400
D) $2,450
E) $2,500
Correct Answer: