The Material Price Variance (Computed at Point of Purchase)is

Question 72

Multiple Choice

The material price variance (computed at point of purchase) is


A) the difference between the actual cost of material purchased and the standard cost of material purchased.
B) the difference between the actual cost of material purchased and the standard cost of material used.
C) primarily the responsibility of the production manager.
D) both a and c.