Multiple Choice
Wimberley Company
Wimberley Company has the following information available for December when 3,500 units were produced (round answers to the nearest dollar) .
Refer to Wimberley Company.What is the labor efficiency variance?
A) $2,050 F
B) $2,050 U
C) $2,040 U
D) $2,040 F
Correct Answer:

Verified
Correct Answer:
Verified