Multiple Choice
Buckingham Company
Buckingham Company uses a standard cost system for its production process and applies overhead based on direct labor hours.The following information is available for May when Buckingham produced 4,500 units:
Standard: | |
DLH per unit | 2.50 |
Variable overhead per DLH | $1.75 |
Fixed overhead per DLH | $3.10 |
Budgeted variable overhead | $21,875 |
Budgeted fixed overhead | $38,750 |
Actual: | |
Direct labor hours | 10,000 |
Variable overhead | $26,250 |
Fixed overhead | $38,000 |
Refer to Buckingham Company.Using the three-variance approach,what is the efficiency variance?
A) $9,937 F
B) $2,187 F
C) $2,187 U
D) $2,937 F
Correct Answer:

Verified
Correct Answer:
Verified
Q94: A one-variance approach calculates only a total
Q95: The following information is available from
Q96: Roberts Company<br>Roberts Company has the following
Q97: Texas Metal Company<br>Texas Metal Company has
Q98: The difference between budgeted variable overhead for
Q100: The difference between budgeted and applied fixed
Q101: Brennan Company<br>The following information is for
Q102: Wimberley Company<br>Wimberley Company has the following
Q103: The variancemost useful in evaluating plant utilization
Q104: The sum of the labor mix and