Buckingham Company
Buckingham Company uses a standard cost system for its production process and applies overhead based on direct labor hours.The following information is available for May when Buckingham produced 4,500 units:
Standard: | |
DLH per unit | 2.50 |
Variable overhead per DLH | $1.75 |
Fixed overhead per DLH | $3.10 |
Budgeted variable overhead | $21,875 |
Budgeted fixed overhead | $38,750 |
Actual: | |
Direct labor hours | 10,000 |
Variable overhead | $26,250 |
Fixed overhead | $38,000 |
Refer to Buckingham Company.Using the four-variance approach,what is the volume variance?
A) $3,125 F
B) $3,875 F
C) $6,063 U
D) $3,875 U
Correct Answer:

Verified
Correct Answer:
Verified
Q59: In a standard cost system,when production is
Q60: Industrial Solutions Company<br>Industrial Solutions Company manufactures a
Q61: The difference between total actual cost incurred
Q62: Wimberley Company<br>Wimberley Company has the following
Q63: Cibolo Company<br>Cibolo Company has the following
Q65: The difference between budgeted and applied fixed
Q66: A flexible budget is an effective tool
Q67: Ideal standards generally yield unfavorable variances.
Q68: An operations flow document shows all processes
Q69: Under the two-variance approach,the volume variance is