Multiple Choice
When the auditor concludes that a control is functioning properly when,in fact,it is not,the auditor has committed the:
A) Risk of underreliance.
B) Risk of overreliance.
C) Risk of incorrect acceptance.
D) Risk of incorrect rejection.
Correct Answer:

Verified
Correct Answer:
Verified