Multiple Choice
Which management tool is used for diagramming the interdependencies between project activities,showing the sequence and duration of each activity?
A) Pareto charts
B) Gantt charts
C) Interrelationship digraphs
D) PERT charts
Correct Answer:

Verified
Correct Answer:
Verified