Compute the MIRR Statistic for Project J and Advise Whether
Question 11
Question 11
Multiple Choice
Compute the MIRR statistic for Project J and advise whether to accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10 percent.Project J Time Cash Flow 0−$1,0001$3002$1,4803−$5004$3005−$100
A) The project's MIRR is 14.77 percent and the project should be accepted. B) The project's MIRR is 9.29 percent and the project should be rejected. C) The project's MIRR is 13.76 percent and the project should be accepted. D) The project's MIRR is 15.31 percent and the project should be accepteD. Year Cash Flow Present Value (If Negative) Sum of PV Future Value (If Positive) Sum of FV Modified CFs 0−$1,000−$1,000−$1,437.75−$1,437.751$300439.232$1,4801969.883−$500−375.664$300330.005−$100−62.09$2.739.11$2.739.11